| From $20 million up to, but not including, $70 million 12 |
• EA submits bid/PQ evaluation report to ADB (SD/RM)
• SD/RM sends copy of evaluation report within 1 working day to PFP1/PFP2 for parallel review
• SD/RM and PPFD will prepare written comments within 5 working days
• SD/RM consolidates comments and prepares the draft procurement approval form or if appropriate a draft response to the executing agency requesting clarification/(s) within 1 working day
• If clarifications are required, SD/RM sends clarification/(s) to executing agency within 1 working day and awaits response for input into the draft procurement approval form, or
• SD/RM sends completed procurement approval form to PFP1/PFP2
• SCD gives no-objection to EA action, with countersignature or endorsement from PFP1/PFP2 Director. PFP1/PFP2 director may delegate authority to a senior PPFD outposted staff
• If SD/RM and PFP1/PFP2 disagree, case elevated to the Procurement Committee.
• SD/RM and PFP1/PFP2, may seek OGC opinion
• SD/RM shall ensure ADB action within a total of 8 working days
| Same procedure as for prior review but the review includes the bidding documents issued. |