3 For loans, copies are provided to Vice-President (to be decided by the respective director general); Director General and Group Chief, Sectors Group; Director General, Regional Department; Deputy Director General and Deputy Group Chief, Sectors Group; Deputy Director General, Regional Department; Assistant Controller, Loan Administration Division; Assistant General Counsel, Office of General Counsel; Director, Procurement Division 1 or 2; Director, Public Financial Management Division 1 or 2; Director, Portfolio Management Division; Regional Head, Operations Coordination; relevant country and/or sector directors; relevant country operations heads; Director, Partner Funds Division of the Climate Change and Sustainable Development Department (if project is cofinanced); mission members. The mission leader has flexibility to include other staff. For developing member country (DMC)- specific and regional TAs, copies are provided to regional head, operations coordination, country operations head, and country director and relevant departments/offices. For multiregion TAs, the mission leader will decide on the relevant departments/offices to be copied.
|
| Documentation Prepared After the Mission |
|
|
A back-to-office report (BTOR) (not more than three pages) with the memorandum of understanding (MOU)2/aide-mémoire and revised project administration manual (PAM) attached. The BTOR is submitted by the mission leader within 5 working days of the mission's return. The mission finalizes the PAM immediately after its return (PAI 1.06: Project Administration Manual).
|
|
A BTOR (not more than three pages) with the MOU/aide-mémoire and PAM, as necessary, attached. It is submitted by the mission leader within 5 working days of the mission’s return. Appendixes and attachments need not be circulated but made available upon request.
|
|
A BTOR (not more than five pages) with the MOU/aide-mémoire and PAM, as necessary, attached, is submitted by the mission leader within 10 working days of the mission’s return. It highlights mission findings, recommendations, and time-bound action plan.
|
Special project administration
|
A BTOR (not more than three pages) is submitted by the mission leader within 5 working days of the mission’s return.
|
Project completion review
|
A BTOR (not more than three pages) is submitted by the mission leader within 10 working days of the mission’s return in consultation with the country operations head to the SD. The Mission should subsequently finalize the project completion report. An MOU/aide-mémoire is recommended.
|
| Documentation Prepared After the Mission |
|
Technical assistance (TA) inception
|
A BTOR (not more than three pages) indicating the results of tripartite discussions and final work program of all concerned parties. It is submitted by the mission leader within 5 working days of the mission's return in consultation with the country operations head (where the mission was fielded for single country and regional TAs) to the TA supervising unit (TASU) director or head through the TASU PAU head with copies to all concerned. Only one BTOR is prepared if the TA is implemented together with the loan.
|
|
A BTOR (not more than three pages) indicating the progress of activities, problems, and issues on TA implementation based on the discussions with executing agencies3 and the consultants on a tripartite or bilateral basis is submitted by the mission leader within 5 working days of the mission’s return to the TASU director or head through the TASU PAU head with copies to all concerned. Only one BTOR is prepared if the TA is implemented together with the loan.
|
Special TA administration
|
A BTOR (not more than three pages) indicating the agreement and or remedies to major problems and issues of TA implementation is submitted by the mission leader within 5 working days of the mission’s return to the TASU director or head through the TASU PAU head with copies to all concerned. Only one BTOR is prepared if the TA is implemented together with the loan.
|
Regional training program activities
|
A BTOR (not more than three pages) is prepared. The BTOR is submitted by the mission leader within 5 working days of the mission’s return to Director General, Procurement, Portfolio, and Financial Management Department; Controller; or TASU director or head with copies to all concerned.
|
|
|
|
{Insert staff to whom the BTOR should be submitted, guided by PAI.
Typically it is the SD.}
|
Cc: CD, COH, Sector PAU Head, mission members as listed
|
|
|
|
|
|
{Select from standard mission types}
|
|
{DD/MMM/YYYY} to {DD/MMM/YYYY}
|
|
|
|
|
|
|
Brief description of the project; implementation status (including compliance with covenants; project rating;
|
|
Mission findings; issues requiring guidance; recommended action plan and next steps
|
|
|
- Project SovOps/eOps record [link]
- Key officials met [link]
- Other attachments as required [link]
|
{Optional. Delete if not applicable}
Items for approval through this BTOR if any
(In general, approval items should be kept separate from BTOR. Only if PTL wants to seek formal approval as per SIs and PAIs through this BTOR, then include here.)
|
Example: Minor change in project involving changes to DMF… {description}
|
| {if any clearance is needed} |
| {Name of staff}, COH |
| {Name of staff}, SD |
|  |
Example: Extension of loan closing date by less than 2 years… {description}
|
| {if any clearance is needed} |
| {Name of staff}, SD |
| {Name of staff}, CD |
|  |
|  |
Feedback/ comments
(It is good practice for the issuer to seek feedback/ comments from the RM and sector office. Comments may be provided in parallel.)
|
{Name of staff, Sector Director, dd mmm yyyy}
Thank you for a good BTOR. Please continue to pay attention to the safeguard issues.
|
|
{Name of staff, Country Director, dd mmm yyyy}
Thank you for a good BTOR. Please continue to coordinate with the EA.
|
|
{Name of staff, Sector PAU Head, dd mmm yyyy}
Thank you for a good BTOR. Please continue to pay attention to the safeguard issues.
|
|
{Name of staff, COH, dd mmm yyyy}
Please make sure to update the Finance Minister by July.
|
|
|  |