Action/Decision | Prior Review Process | Post Review |
(1) $50 million and above | · Full review based on ADB standard bidding documents prior to issuance of actual bidding document by EA:
o SD/RM1 and PPFD to review all sections in parallel;
o OGC comments on contract conditions in parallel
o Comments of OGC/PPFD provided to SD/RM within 5 working days for consolidation and transmittal to EA within 2 working days from receipt of comments,
o SD/RM to convey consolidated comments to EA within 1 working day for a total of 8 working days from receipt of bidding documents
· Option for subsequent bidding documents of similar contract type:
(i) Same reviewers but review after issuance by EA
(ii) EA submits immediately to ADB issued BD
(iii) ADB consolidated comments within 8 working days to EA with recommendation to amend BD, if any, as well as possible deadline extension
| NA |
(2) Below $50 million (except for post review (sampling)) | · SD/RM reviews based on ADB standard bidding documents and issues no-objection to issue bidding document to EA, subject to:
o PPFD/OGC endorsement when BDs have exceptions to MBD, or
o SD/RM with PPFD/OGC advice when requested for other specific issues, or
o SCD2 gives no-objection, with endorsement from PASS accredited staff
o SD/RM sends comments to EA within 8 working days
· For subsequent bidding documents of similar contract type:
(i) Same reviewers but review after issuance by EA
(ii) EA submits immediately to ADB the issued BDs
(iii) SD/RM sends comments within 8 working days to EA with recommendation to amend BD, if any, as well as possible deadline extension
· SD/RM may adopt streamlining measure for similar contracts | · Review is undertaken together with bid evaluation and award documents. |
Action/Decision | Prior Review Process (Prior to award) | Post Review (After award) |
(1) $50 million and above | · EA submits bid/PQ evaluation report to ADB (SD/RM)
· SD/RM, OGC and PPFD review in parallel with review completion target of 10 working days
· Procurement Approval Form submitted to Procurement Committee for no-objection
· (see PAI 3.10 for detailed procedures) | NA |
(2) $20million to $50 million | · EA submits bid/PQ evaluation report to ADB (SD/RM)
· SD/RM sends copy of evaluation report to PFP1/PFP2 for review
· PFP1/PFP2 provides comments within 5 working days
· SD/RM prepares Procurement Approval Form within 1 working day and sends completed Form to PFP1/PFP2
· SCD gives no-objection to EA action, with countersignature/endorsement from PFP1/PFP2 Director. PFP1/PFP2 director may delegate authority to senior PPFD outposted staff.
· If SD/RM and PFP1/PFP2 disagree, , case elevated to the Procurement Committee
· SD/RM shall ensure ADB action within total of 8 working days from receipt of bid/PQ evaluation report, except if the matter is elevated to procurement committee | NA
(Note: For exceptional cases where post review is approved for contract sizes in this range, the same procedure as for prior review will apply.) |
(3) Up to $20million | · SD/RM reviews and SCD gives no-objection to EA action, with endorsement from PASS accredited staff within 8 working days
· SD/RM may consult PPFD/OGC on specific issues or request PC review | Same procedure as for prior review. |