PROJECT ADMINISTRATION INSTRUCTIONS
PAI No. 3.11
Revised on June 2022



PROCUREMENT CONTRACT MONITORING, SUPERVISION, AND REVIEW

A. Monitoring Procurement Contracts

1. Once fully operational, the Procurement Review System or PRS will be the main monitoring system for the procurement of contracts.

B. Contract Modifications

2. During the course of administering a works, goods, or design-supply-install contract, it may become necessary to modify the contract to do the following:
      1 Changes in the contract price brought about by the application of the price adjustment mechanism specified in the contract are not considered contract modifications.

3. Contract modifications must be approved by ADB in accordance with the following procedures. Prior ADB approval is required for modifications to contracts subject to prior review.2 For contracts subject to post review, ADB approves contract modifications on an ex post facto basis. With respect to contracts subject to post review, if the sector director, country director, or procurement committee, as applicable, fails to respond to any time extension or modification request within 6 months of receipt of the required documents, then ADB shall be deemed to have given its no-objection to the contract modification unless it has specifically informed the borrower otherwise.

      2 Prior approval is not required in extreme emergencies.

4. For contract modifications covered by para. 3 (iii) and (iv) of this PAI, staff should note that contract variation/change orders beyond the normal limits set in the original contract take the character of direct contracts for which justifications are required to be in accordance with Part C of PAI 3.06 (Other Methods of Procurement).

5. Staff shall seek and obtain OAI endorsement prior to approving any modification of a contract involving a sanctioned firm or individual, to ensure that the contract modification is not considered an attempt to circumvent sanctions.

6. After approval of the contract modification, the project division will issue an update of the executing agency (EA) contract record by issuing a Procurement Contract Update Sheet (PCUS) in the Loan/Grant Financial Information System (LFIS/GFIS). The reason for the contract modification and data such as the original contract amount and completion date should also be indicated in the PCUS for future reference as should any extension of time.

C. Contract Termination

7. When an EA proposes to terminate a contract, it sends a recommendation to ADB. Staff should note there are specific procedures for terminating contracts under the conditions of contract, and should ensure that the EA has complied, before endorsing contact termination.


8. The sector division or resident mission in both cases should prepare a memorandum justifying or rejecting the EA request to terminate the contract.

9. Staff shall remind EAs that when the remaining portions of the terminated contract will undergo rebidding, they should proceed immediately to technically assess the remaining scope to provide the basis for preparing the rebidding documents. These documents shall also instruct bidders to visit and inspect the site and the condition of the completed portions, if any.

D. Procurement Review for Effective Implementation

10. A procurement review for effective implementation (PREI) should ideally be undertaken during implementation when approximately half of the contracts in the procurement plan have been procured, preferably as part of the midterm review to evaluate key indicators and risks that are associated with the EA’s procurement performance. In such a case, the Director of PFP1/PFP2 may carry out a PREI in consultation with the project division director. The PREI will validate and reassess the results of the EA capacity and procurement risk assessment that were conducted during CPS and project processing, and will update or modify procurement risk ratings. Based on the findings and ratings of the PREI, ADB may: (i) require adjustments in the EA procurement plan such as on the prior review thresholds and procurement methods; and (ii) agree with the EA to adopt an action plan to build capacity and mitigate risks within the prescribed period.3

      3 The PREI user’s guide and manual are available in OpsPedia through this link: https://myadb.adb.org/wps/myportal/home/departments/ppfd/searchresult/!ut/p/z1/hVLJboMwEP0VXzhWHghhOZK NkGbpIkjwpbLZ5JYY4pCFfn1NmksrJfHFmvF7b2beGBO8wUTQIy9owytBSxXHxPqYTJbe7NnXwTFXDnhhX3f7K9 CDRQ- vL4DlyggnZqDrjjXWwbCm5mAeBeCPepjc4ZvWlQ83jgeP- BGO_QGO5bn0RsVV7U675H6xNSZ_C_qzl75ScN2e_TqH1dD4D4D56xC8cbQMo2Gg8PYVcM- RR11MAc8wKcqK_W6Af- 52xMMkqUSTnRu8Sap9hS6RaFDJmaSy1YCmDHGVk2pxGqRZTWWzVYi9Bh1BgzKjUnBRICpSlNCaJrxpETvwM lVZDRpJ- eU9ryTKqAbQVxeqZZUcZNZJIZkdeXba41gZbd80OlT_osPhUFRyq4Z474auE57i2HFtO2cApmUZJs106uZGzhzbc hzGUmbjehuGon36epue2t73YPEDxcBnYw!!/dz/d5/L2dBISEvZ0FBIS9nQSEh/