Close CloseAsk Question Ask QuestionView  Q & A View Q & APrint Print

PROJECT ADMINISTRATION INSTRUCTIONS
PAI No. 5.02
Revised on June 2024


CHANGE IN LOAN PROJECTS1

      1 In this PAI, the term “loan(s)” includes grant(s) and the term “project(s)” includes program(s), unless the context requires otherwise. This PAI also applies to loans from external sources that are administered by ADB, unless agreed otherwise between ADB and cofinancier(s).

1. Projects are expected to be implemented as approved by the Asian Development Bank (ADB). However, flexibility may be required to allow for changes to the project’s scope,2 implementation and financial arrangements, in response to unexpected changes in circumstances during implementation. This would include changes that would improve the development impact and reflect stakeholder interests during implementation.

      2 Scope refers to investment and/or activities including capacity development actions to achieve the project outcome.

2. This Project Administration Instruction (PAI) describes how changes proposed by the borrower3 and/or ADB to a sovereign loan are approved.4 This PAI should be read in conjunction with (i) PAI 4.01 (Suspension and Cancellation of Loans); (ii) PAI 5.03 (Reallocation of Loan Proceeds, Change in Counterpart Funding and Change in Disbursement Percentage);(iii) PAI 5.04 (Utilizing Surplus Loan Proceeds);(iv) PAI 5.05 (Project Cost Overruns for Loan Projects);and (v) Operations Manual (OM) Section D14 (Multitranche Financing Facility) and relevant staff instructions for changes in multitranche financing facility (MFF). This PAI is not applicable to changes due to, or that cause, additional financing (OM Section H5 [Additional Financing])and is not applicable to changes that relate to the release of tranches under policy-based loans (OM Section D4 [Policy-based Lending]).

      3 In this PAI, the term “borrower” also refers to recipients of grants, executing agencies, and/or implementing agencies, unless the context requires otherwise.
      4 Change in nonsovereign projects is addressed in OM Section D10 (Nonsovereign Operations).Change in technical assistance projects is addressed in PAI 5.08 (Administering Technical Assistance).

A. Definition of Major and Minor Change

3. A major change materially alters or fundamentally affects the approved scope and project outcome.

4. A minor change is defined as any change with respect to an ADB approved project that does not result in a major change. Minor changes include but are not limited to changes to the project’s cost estimates5 and financing plan,6 changes to project outputs or their performance target(s), changes in implementation arrangements, including changes in the executing and/or implementing agencies, implementation period, procurement and consulting services,7 disbursement arrangements, and reporting arrangements, including project performance monitoring and evaluation. Changes made to design and monitoring framework (DMF) outcome indicators which do not materially alter or fundamentally affect the approved project scope and outcome may be processed as a minor change.8

      5 A change to the cost estimates refers to changes among the existing categories of the project’s cost and financing tables.
      6 A financing plan is defined as “the plan which identifies the different sources of financing for the project; if appropriate in relevant cases, it will also describe the different loan currencies and lending terms (i.e., short-term, medium-term, and long-term maturities)”
      (OM Section H3: Cost Sharing and Eligibility of Expenditures for ADB Financing).
      7 Except for changes to the procurement plan that increase or decrease the number of contracts, decrease or increase the estimated value of contracts, or merely adopt the procurement method thresholds in Appendix 2 of PAI 3.03 (International Competitive Bidding) or Staff Instruction on Borrower-Administered Procurement.These do not require processing a minor change under this PAI and instead, are explained and processed through the Procurement Review System.
      8 Common examples of outcome indicator changes considered minor in scope include the addition of new or strengthened indicators to measure the project’s outcome made possible by the availability of improved data, refinement of outcome indicators to increase their specificity or accuracy, revision of outcome indicators or their targets to a higher level of ambition.

B. Approval and Reporting

5. When proposing a change, due diligence is conducted for the scope or implementation arrangements affected by the change and the following matters are confirmed with the relevant project team members and other supporting departments/offices concerned:9

      9 For project team members and other supporting departments/offices, refer to Staff Instruction on Business Processes for Sovereign and Sovereign-Guaranteed Financing.
      10 In the specific case of a project cofinanced by a trust fund that is jointly managed by CCPF and another department/office, the concurrence of both CCPF and that department/office has been obtained.
      11 Staff Instruction on Borrower-Administered Procurementare effective for projects or delegated technical assistance with concept papers approved after 1 July 2017.
      12 When changes occur regarding implementing arrangements, the Office of the Anticorruption and Integrity should be consulted on the integrity due diligence requirement.

6. The project team leader (PTL) should request relevant project team members to review within their functional areas to assure due diligence. The project team members proactively contribute to and take responsibility within their functional area. The project team members will seek guidance and clearance from their functional reporting line, where necessary. The PTL retains the overall responsibility for ensuring compliance with relevant due diligence requirements.

7. In addition to the contribution from the project team members in their respective functional areas, the PTL should consult with other supporting departments/offices to ensure relevant due diligence, if applicable. The role of other supporting departments/offices is to review the proposed change as necessary, provide advice and support to the project team in meeting the requirements in their respective functional areas.

8. If there are remaining unresolved issues between the PTL and the concerned department/office, the sector director (SD) convenes a resolution meeting at the request of the PTL or director/head from concerned department/office to resolve the issues. The SD will chair the resolution meeting, facilitate the resolutions, and make the decision to proceed with the proposed change following the procedures outlined in paras. 9–11 and approval authorities in Table 1 or instruct the project team to take further actions.13

      13 For major change, the resolution meeting is chaired by the regional director general (RDG) for track 1 projects or regional vice-president for track 2 projects following the Staff Instruction on Business Processes for Sovereign and Sovereign-Guaranteed Financing.

9. DMF-related minor change in a project. For minor changes requiring changes to the DMF outputs, indicators for outcome and outputs, and output weights in eOperations, the PTL should prepare a draft memorandum in consultation with the sector project administration unit head following the template provided in Appendix 114 and conduct due diligence specified in paras. 5–7. The SD, with the concurrence of the country operations head (COH), approves the memorandum (Table 1).

      14 Or equivalent template following the initiative of the departments/offices to streamline the preparation of the memorandum.

10. Non-DMF-related minor change in a project. For other minor changes that are non-DMF-related, the PTL can approve such changes after conducting due diligence as specified in paras. 5–7. The PTL should consult with the sector project administration unit head, if needed. The PTL should record the changes with reasons/justifications in project documents such as back-to-office report, project administration manual or equivalent if project administration manual is not applicable for some modalities, memorandum of understanding, aide-mémoire, and ADB's no-objection letter. The project team informs relevant departments/offices of the change.

11. Major change in a project. The project team will prepare a draft Board paper, in consultation with the regional head, operations coordination (RHOC) and COH, following the major change template provided in Office of the Secretary Information Access Unit’s SharePoint site: Board Documents Templates and conduct due diligence as specified in paras. 57. The SD submits the draft Board paper to the senior sector director (SSD) for endorsement. After endorsement, the project team submits the draft Board paper to the Office of the Secretary for editing and clearance. The edited Board paper (on a no-objection basis) is submitted by the SD through the SSD, regional director general (RDG), and regional vice-president for the President’s approval to circulate to the Board (Table 1).

12. If determination of whether the proposed change is major or minor is inconclusive, the SSD decides in consideration of the views from RHOC, OGC, SPD and the Procurement, Portfolio, and Financial Management Department (PPFD).

13. Major change in cofinanced loans administered by ADB. The PTL should prepare a draft memorandum following the template provided in Appendix 1 and conduct due diligence as specified in paras. 5–7. The SD submits the memorandum through the RDG and regional vice-president to the President for approval (Table 1).

14. Multitranche Financing Facility. Changes to the MFF can occur at two levels: the tranche level or the facility level.
      15 Extensions to the availability period of legacy MFFs up to the 10-year maximum follow Table 1. See PAI 4.02 (Loan Closing Dates).

15. Project Readiness Financing (PRF). A change in PRF may include changes to a project readiness loan’s scope and implementation arrangements, including implementation period. A change in a PRF is considered major if the proposed change fundamentally alters the overall objective of such financing, otherwise the change is considered minor.16 The PTL should conduct due diligence specified in paras. 5–7 and follow procedures outlined in paras. 9–11 and approval authorities in Table 1.

      16 For example, a major change may include changing the scope of a project readiness loan which is supporting the preparation of an investment master plan for the transport sector and delivery capacity development support to strengthen a government agency’s project implementation capacity, to instead using the PRF to finance the detailed engineering design of a complex hydropower project with significant anticipated environmental and social impacts, and high vulnerability to climate change.

16. Small Expenditure Financing Facility (SEFF). After approval, the borrower may from time to time propose changes to the facility, or to an approved Activity. A change to the facility is considered major if the proposed change (i) fundamentally alters the scope of activities, and the nature of expenditures, to be financed under the SEFF;17 (ii) an Activity is categorized as ‘A’ for environment, resettlement, and/or indigenous people in line with ADB’s Safeguard Policy Statement (2009); and/or (iii) results in an overall increase in the facility size. Otherwise, the change is considered minor. The PTL should conduct due diligence specified in paras. 5–7 and follow procedures outlined in paras. 9–11 and approval authorities in Table 1.

      17 For example, if it is proposed to increase the scope of an existing facility to cover ongoing project support and post-project completion support, in addition to project preparation support
Table 1: Approval and Concurrence Authorities for Proposed Change

Change in
Major Change
Minor Change (DMF-related)
Approver
Concurrer(s)
Approver
Concurrer(s)
    (i) Loan financed projects (excluding projects under MFF)
    Board
    (i) SSD, (ii) RDG in consultation with CD, (iii) RVP, and (iv) President
    SD
    COH
    (ii) Loans sourced from cofinancing
    President
    (i) SD, (ii) RDG in consultation with CD, and (iii) RVP
    SD
    COH
    (iii) MFF at the facility level
    Board
    (i) SSD, (ii) RDG in consultation with CD, (iii) RVP, and (iv) President
    Presidenta
    (i) SD, (ii) RDG in consultation with CD, and (iii) RVP
    (iv) MFF at the tranche level
    President
    (i) SD, (ii) RDG in consultation with CD, and (iii) RVP
    SD
    COH
    (v) PRF
    Board
    (i) SSD, (ii) RDG in consultation with CD, (iii) RVP, and (iv) President
    SD
    COH
    (vi) Small-scale PRFb
    RVP
    SD and RDG in consultation with CD
    SD
    COH
    (vii) SEFF at the facility level
    Board
    (i) SSD, (ii) RDG in consultation with CD, (iii) RVP, and (iv) President
    SD
    COH
    (viii) SEFF Activity
    SSD
    CD
    SD
    COH
CD = country director; COH = country operations head; DMF = design and monitoring framework; MFF = multitranche financing facility; PRF = project readiness financing; RDG = regional director general; RVP = regional vice-president; SD = sector director;
SEFF = small expenditure financing facility; SSD = senior sector director.
Note: Non-DMF-related minor change follows para. 10 except non-DMF-related minor change for MFF at the facility level which requires approval of the RDG with the concurrence of the SD.
aExtension of availability period for legacy MFFs up to 10 years from the MFF approval date will follow the process for a DMF-related minor change in MFF at the facility level.
bSmall-scale PRF does not exceed $15 million.

17. After approval of the major or minor change, the project team will send a copy of the Board paper, approved memorandum, or recorded documents to COH, RHOC, CTL, OGC, Portfolio Management Division of PPFD, SPD, and Office of Anticorruption and Integrity for MFF or a tranche under an MFF, CCPF if the project is cofinanced; and other relevant departments/offices for information. The project team will also update the project/facility administration manual and the eOperations project record. OGC will make any necessary amendments to the financing agreements. For any changes involving the cofinanced portion of the project, CCPF will coordinate the amendment to the cofinancing agreements as needed. Major change documents approved by the Board and updated project/facility administration manual will be disclosed in line with ADB’s Access to Information Policy. The project team should submit a Loan and Grant Milestone and Change Event (LGMCE) form to CTL, if necessary, for proper recording.18

      18 See PAI 6.04 (Loan Milestone and Change Event).

18. All approved major and DMF-related minor changes are reported by PPFD to the Board in the quarterly portfolio updates. Changes in an MFF and/or tranche under an MFF are also reported annually to the Board by SPD.

C. Transfer of Loan Administration and Supervision

19. When the loan administration and supervision need to be transferred from the current sector office to another sector office, the senior sector directors of the current and the successor sector offices should agree by email in consultation with relevant RHOC, with copy to the Director General and Group Chief, Sectors Group; Portfolio Management Division of PPFD; Loan Administration Division of the Controller's Department (including LGMCE form); SPD; and CCPF if cofinanced. The email should be recorded in the project folder.
Appendix 1

{This template is used for a (i) DMF-related minor change; or (ii) major change not approved by the Board }


FOR APPROVAL OF PARA. 1

To:

Through:

From:

Subject: {Loan xxxx and/or Grant xxxx, MFF xxxx - DMC: Project Title}

A. Matter for Consideration

1. State precisely the proposed [minor or major] change.

B. Background

2. Indicate the [loan or grant amount and dates of approval and signing, loan effectiveness, and loan closing] or [MFF amount, date of approval, and availability period].

3. Describe the project outcome and outputs and provide names of agencies involved in the implementation.

C. Status of Implementation

4. Describe the implementation status, what has been done and what remains to be done (including contract awards, disbursement, financial management arrangements, and project rating status).

D. Proposed Change of the [Project] / [MFF] / [Individual Tranche under an MFF]

5. Describe the proposed change and the reasons for it. Describe the implications for the cost, the financing plan, project and entity financial viability and sustainability, implementation schedule, disbursement and financial management arrangements, project benefits, implementation and procurement arrangements, and design and monitoring framework, where applicable.

E. Staff Views

6. Confirm compliance with appropriate provisions of PAI 5.02, paras. 57.

{Attachments: Include revised design and monitoring framework, financing plan, detailed cost estimates, reallocation of loan proceeds, and financial management assessment report, where applicable.}


cc: Vice-President (relevant region) for Major Change Regional Head, Operations Coordination
Country Director CCPF (if there is cofinancing)